Total facility capacity target
Company: Marathon Digital - Project: Hardin
The claim, verbatim
The data center facility will have a capacity of up to 100 megawatts
Source (primary)
Marathon Digital 8-K filed 2020-10-13 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “designing and developing a data center facility of up to 100-megawatts”
How we checked this
Checked on September 23, 2026. The cited source supports every part of this claim.
The filing states Beowulf and 2P1 have been designing and developing a data center facility of up to 100 megawatts.
Confirmed in the source:
- The data center facility is being designed and developed with a capacity of up to 100 megawatts
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000149315220019373/form8-k.htm) in full (7,161 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Marathon Digital 8-K filed 2020-10-13
Quote: “designing and developing a data center facility of up to 100-megawatts”