Total facility capacity target

Company: Marathon Digital - Project: Hardin

Subject kind
facility capacity
Statement date
2020-10-12
Promised amount
100.0 MW
Current status
stated

The claim, verbatim

The data center facility will have a capacity of up to 100 megawatts

Source (primary)

Marathon Digital 8-K filed 2020-10-13 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “designing and developing a data center facility of up to 100-megawatts”

How we checked this

Checked on September 23, 2026. The cited source supports every part of this claim.

The filing states Beowulf and 2P1 have been designing and developing a data center facility of up to 100 megawatts.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000149315220019373/form8-k.htm) in full (7,161 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Marathon Digital 8-K filed 2020-10-13

Quote: “designing and developing a data center facility of up to 100-megawatts”

View cached copy (2026-09-13)Live source ↗