Antminer delivery schedule from Bitmain

Company: Riot

This claim was marked delayed on September 15, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2021-04-06
Promised by
2021-11-01
Promised amount
3500.0 units
Current status
delayed

The claim, verbatim

Bitmain is scheduled to deliver 12 batches of approximately 3,500 miners each on a monthly basis between November 2021 and October 2022

Source (primary)

Riot 8-K filed 2021-04-07 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “Bitmain is scheduled to manufacture these new Miners in 12 batches of approximately 3,500 Miners (each, a "Batch"), which will be delivered, on a monthly basis, between November 2021 and October 2022”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Riot 8-K filed 2021-04-07

Quote: “Bitmain is scheduled to manufacture these new Miners in 12 batches of approximately 3,500 Miners (each, a "Batch"), which will be delivered, on a monthly basis, between November 2021 and October 2022”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.