Antminer delivery schedule from Bitmain

Company: Riot

Subject kind
facility timeline
Statement date
2021-04-06
Promised by
2021-11-01
Promised amount
3500.0 units
Current status
verified

What the later record shows

Delivered; the record does not say when

Deliveries were scheduled monthly from November 2021 to October 2022. Later filings show the remaining S19j-Pro deliveries running through December 2022, and all 2021-agreement miners arrived by January 2023. The passages don't show whether this agreement's final batch arrived by October 2022.

“a total of 41,601 new S19j-Pro model miners and 30,000 new S19XP model miners, scheduled to be delivered through December 2022”
2022-05-09 · Riot 10-Q filed 2022-05-10 View cached copy (2026-09-13)Live source ↗
“All miners subject to these purchase orders were delivered through December 31, 2022, except for 5,130 miners, which were delivered in January 2023.”
2023-03-01 · Riot 10-K filed 2023-03-02 View cached copy (2026-09-13)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Bitmain is scheduled to deliver 12 batches of approximately 3,500 miners each on a monthly basis between November 2021 and October 2022

Source (primary)

Riot 8-K filed 2021-04-07 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “Bitmain is scheduled to manufacture these new Miners in 12 batches of approximately 3,500 Miners (each, a "Batch"), which will be delivered, on a monthly basis, between November 2021 and October 2022”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The filing states that Bitmain will manufacture the miners in 12 batches of about 3,500 each, delivered monthly from November 2021 through October 2022.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1167419/000107997321000253/riot_8k-040621.htm) in full (12,274 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot 8-K filed 2021-04-07

Quote: “Bitmain is scheduled to manufacture these new Miners in 12 batches of approximately 3,500 Miners (each, a "Batch"), which will be delivered, on a monthly basis, between November 2021 and October 2022”

View cached copy (2026-09-13)Live source ↗

confirms Riot 10-K filed 2023-03-02

Quote: “All miners subject to these purchase orders were delivered through December 31, 2022, except for 5,130 miners, which were delivered in January 2023.”

View cached copy (2026-09-13)Live source ↗

confirms Riot 10-Q filed 2022-05-10

Quote: “a total of 41,601 new S19j-Pro model miners and 30,000 new S19XP model miners, scheduled to be delivered through December 2022”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.