Hardin Montana data center Phase II - 30 MW capacity

Company: Marathon Digital - Project: Hardin

Subject kind
facility capacity
Statement date
2021-05-09
Promised amount
9000000.0 USD
Current status
stated

The claim, verbatim

Phase II of the Hardin, Montana data center accounts for 30 MW and is anticipated to cost approximately $9 million.

Source (primary)

Marathon Digital 10-Q filed 2021-05-10 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “Phase II accounts for 30 MW of the 100 MW project and is anticipated to cost approximately $9 million.”

How we checked this

Checked on September 22, 2026. The cited source supports every part of this claim.

The document states the 30 MW Phase II figure and the approximately $9 million cost.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000149315221010910/form10-q.htm) in full (105,149 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Marathon Digital 10-Q filed 2021-05-10

Quote: “Phase II accounts for 30 MW of the 100 MW project and is anticipated to cost approximately $9 million.”

View cached copy (2026-09-13)Live source ↗