Bitmain mining equipment order
Company: Applied Digital
What the later record shows
Outcome not yet confirmed · happened March 9, 2022
The 200PH Bitmain order was still described as 'due late in calendar year 2021' in February 2022 with no delivery reported. The company stopped mining on March 9, 2022 and planned to sell undelivered purchased equipment.
“as evidenced by our order through Bitmain for 200PH of mining equipment due late in calendar year 2021”
2022-02-27 · Applied Digital S-1/A filed 2022-02-28 View cached copy (2026-09-13)Live source ↗
“However, the equipment is either not online or was previously purchased but has yet to be delivered. We intend to sell this equipment as soon as possible”
2022-04-11 · Applied Digital S-1/A filed 2022-04-12 View cached copy (2026-09-13)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Order for 200PH of mining equipment from Bitmain due late in calendar year 2021
Source (primary)
Applied Digital S-1/A filed 2021-11-02 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “our order through Bitmain for 200PH of mining equipment due late in calendar year 2021”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The filing describes an order through Bitmain for 200PH of mining equipment due late in calendar year 2021. It also states separately that the company was purchasing additional mining equipment from Bitmain.
Confirmed in the source:
- Applied Blockchain placed an order through Bitmain for 200PH of mining equipment
- The equipment was due late in calendar year 2021
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000110465921132877/tm2124821-2_s1a.htm) in full (486,363 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital S-1/A filed 2021-11-02
Quote: “our order through Bitmain for 200PH of mining equipment due late in calendar year 2021”