Hardin Montana facility maintenance and upgrades

Company: Marathon Digital - Project: Hardin

Subject kind
facility timeline
Statement date
2022-03-09
Current status
stated

The claim, verbatim

System upgrades on Hardin, MT power generating station beginning November 2021 and continuing into 2022, with each phase requiring approximately 3-5 days of offline time for mining operations, intended to improve efficacy, efficiency, safety, and mitigate future downtime.

Source (primary)

Marathon Digital 10-K filed 2022-03-10 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “system upgrades will be performed on the power generating station beginning in November 2021 and continuing into 2022. Each phase of this maintenance will require the plant, and therefore the Company's mining operations in Hardin, MT, to be offline for approximately three to five days.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Marathon Digital 10-K filed 2022-03-10

Quote: “system upgrades will be performed on the power generating station beginning in November 2021 and continuing into 2022. Each phase of this maintenance will require the plant, and therefore the Company's mining operations in Hardin, MT, to be offline for approximately three to five days.”