jain.com

Hardin Montana facility maintenance and upgrades

Company: Marathon Digital - Project: Hardin

Subject kind
facility timeline
Statement date
2022-03-09
Current status
stated

The claim, verbatim

System upgrades on Hardin, MT power generating station beginning November 2021 and continuing into 2022, with each phase requiring approximately 3-5 days of offline time for mining operations, intended to improve efficacy, efficiency, safety, and mitigate future downtime.

Source (primary)

Marathon Digital 10-K filed 2022-03-10 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “system upgrades will be performed on the power generating station beginning in November 2021 and continuing into 2022. Each phase of this maintenance will require the plant, and therefore the Company's mining operations in Hardin, MT, to be offline for approximately three to five days.”

How we checked this

Checked on September 22, 2026. The cited source supports every part of this claim.

Every detail of the Hardin maintenance plan appears in the document.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000149315222006446/form10-k.htm) in full (385,382 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Marathon Digital 10-K filed 2022-03-10

Quote: “system upgrades will be performed on the power generating station beginning in November 2021 and continuing into 2022. Each phase of this maintenance will require the plant, and therefore the Company's mining operations in Hardin, MT, to be offline for approximately three to five days.”

View cached copy (2026-09-13)Live source ↗