jain.com

82,500 ASIC miners (S19XP, S19j, S19j Pro models) with delivery through December 2022

Company: Riot

Subject kind
product
Statement date
2022-03-15
Promised by
2022-12-31
Promised amount
82500.0 units
Current status
verified

What the later record shows

Delivered late · happened January 31, 2023

All miners under the Bitmain orders were delivered by December 31, 2022 except 5,130, which arrived in January 2023, after the December 2022 schedule.

“All miners subject to these purchase orders were delivered through December 31, 2022, except for 5,130 miners, which were delivered in January 2023.”
2023-03-01 · Riot 10-K filed 2023-03-02 View cached copy (2026-09-13)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Ordered 82,500 ASIC miners from Bitmain (30,000 S19XP, 43,500 S19j, 9,000 S19j Pro) with anticipated monthly delivery through December 2022

Source (primary)

Riot 10-K filed 2022-03-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “we executed additional purchase orders totaling $480 million with Bitmain Technologies Limited ("Bitmain") for an additional 82,500 ASIC miners, including 30,000 of Bitmain's latest generation Antminer model S19XP (140 TH/s) miners, and 52,500 S19j and S19j Pro miners, including 43,500 model S19j (90 TH/s) miners and 9,000 model S19j Pro (100 TH/s) miners, with anticipated monthly delivery and deployment schedules set through December 2022”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The 10-K gives this exact model breakdown and the delivery schedule through December 2022.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1167419/000107997322000280/riot10k1221.htm) in full (467,403 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot 10-K filed 2022-03-16

Quote: “we executed additional purchase orders totaling $480 million with Bitmain Technologies Limited ("Bitmain") for an additional 82,500 ASIC miners, including 30,000 of Bitmain's latest generation Antminer model S19XP (140 TH/s) miners, and 52,500 S19j and S19j Pro miners, including 43,500 model S19j (90 TH/s) miners and 9,000 model S19j Pro (100 TH/s) miners, with anticipated monthly delivery and deployment schedules set through December 2022”

View cached copy (2026-09-13)Live source ↗

confirms Riot 10-K filed 2023-03-02

Quote: “All miners subject to these purchase orders were delivered through December 31, 2022, except for 5,130 miners, which were delivered in January 2023.”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.