Mining capacity target for end of 2022
Company: Riot
The claim, verbatim
Anticipates utilizing approximately 370 MW of capacity by the end of 2022
Source (primary)
Riot 10-K filed 2022-03-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “Based on our existing operations and expected deliveries of miners we have purchased, we anticipate having approximately 120,150 miners in operation, utilizing approximately 370 MW of capacity by the end of 2022.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Riot 10-K filed 2022-03-16
Quote: “Based on our existing operations and expected deliveries of miners we have purchased, we anticipate having approximately 120,150 miners in operation, utilizing approximately 370 MW of capacity by the end of 2022.”