jain.com

1.21 Gigawatts LLC up to 1.5GW capacity

Company: Applied Digital

Subject kind
facility capacity
Statement date
2022-03-20
Promised amount
1.5 GW
Current status
stated

The claim, verbatim

1.21 Gigawatts LLC will develop, construct, and operate Next-Gen datacenters with up to 1.5GW of capacity

Source (primary)

Applied Digital S-1/A filed 2022-03-21 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “1.21 Gigawatts will develop, acquire, construct, finance, operate, maintain and own one or more Next-Gen datacenters with up to 1.5GW of capacity”

How we checked this

Checked on September 22, 2026. The cited source supports every part of this claim.

The document states 1.21 Gigawatts will develop and operate Next-Gen datacenters with up to 1.5GW of capacity.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000110465922036163/tm2124821-21_s1a.htm) in full (555,375 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital S-1/A filed 2022-03-21

Quote: “1.21 Gigawatts will develop, acquire, construct, finance, operate, maintain and own one or more Next-Gen datacenters with up to 1.5GW of capacity”

View cached copy (2026-09-13)Live source ↗