800MW hosting capacity target by May 2023

Company: Applied Digital

This claim was marked delayed on October 9, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
guidance
Statement date
2022-03-27
Promised by
2023-05-31
Promised amount
800.0 MW
Current status
delayed

What the later record shows

The date slipped

A May 2024 filing describes North Dakota capacity reaching only 280 MW once Ellendale is fully energized, plus 90 MW in Texas. That is far short of 800 MW, which implies the May 2023 target was not met; no new date was given.

“Once fully energized, this location will bring the Company to 280 MW of total hosting capacity across its facilities in North Dakota”
2024-05-05 · Applied Digital 424B5 filed 2024-05-06 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Company targeting 800MW of hosting capacity online by May 2023

Source (primary)

Applied Digital S-1/A filed 2022-03-28 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “We are targeting bringing 800MW online by May 2023, 1.8GW by May 2024 and 5GW over the next five years”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

In the Hosting Operation section, the filing states the company is targeting bringing 800MW online by May 2023.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000110465922038726/tm2132377-17_s1a.htm) in full (562,281 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital S-1/A filed 2022-03-28

Quote: “We are targeting bringing 800MW online by May 2023, 1.8GW by May 2024 and 5GW over the next five years”

View cached copy (2026-09-13)Live source ↗

delays Applied Digital 424B5 filed 2024-05-06

Quote: “Once fully energized, this location will bring the Company to 280 MW of total hosting capacity across its facilities in North Dakota”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.