Redeploy Hardin miners to renewable facilities

Company: Marathon Digital - Project: Hardin

Subject kind
facility timeline
Statement date
2022-04-04
Promised by
2022-09-30
Current status
verified

What the later record shows

Delivered on time · happened September 30, 2022

The 2022 10-K states that the Hardin-installed rigs were redeployed to renewable power facilities in Q3 2022, which meets the September 30, 2022 deadline. A large share of the servers was sold rather than redeployed.

“the Company redeployed its Hardin-installed mining rigs to renewable power facilities in the third quarter of 2022.”
2023-03-15 · Marathon Digital 10-K filed 2023-03-16 View cached copy (2026-09-13)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Company will redeploy its Hardin-installed miners to renewable power facilities on or before September 30, 2022

Source (primary)

Marathon Digital 8-K filed 2022-04-05 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “the Company will redeploy its Hardin-installed miners to renewable power facilities on or before September 30, 2022”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The 8-K states the company will redeploy its Hardin-installed miners to renewable power facilities on or before September 30, 2022.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000149315222009124/form8-k.htm) in full (5,267 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Marathon Digital 8-K filed 2022-04-05

Quote: “the Company will redeploy its Hardin-installed miners to renewable power facilities on or before September 30, 2022”

View cached copy (2026-09-13)Live source ↗

confirms Marathon Digital 10-K filed 2023-03-16

Quote: “the Company redeployed its Hardin-installed mining rigs to renewable power facilities in the third quarter of 2022.”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.