Subject kind
financing
Statement date
2022-04-07
Promised by
2022-12-07
Promised amount
75.0 USD
Current status
delayed

The claim, verbatim

Entered into two bridge promissory notes totaling $75 million ($60 million with B. Riley Commercial Capital, LLC and $15 million with an affiliate) maturing December 7, 2022, bearing interest at 7% per annum, amortizing in equal monthly installments starting August 1, 2022

Source (primary)

Core Scientific 8-K filed 2022-04-08 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “entered into two bridge promissory notes, one in an aggregate principal amount of $60 million with B. Riley Commercial Capital, LLC and one in an aggregate principal amount of $15 million with an affiliate of B. Riley Commercial Capital, LLC (the "Notes"). The Notes mature on December 7, 2022, bear interest at a rate of 7% per annum and amortize in equal monthly installments starting on August 1, 2022.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Core Scientific 8-K filed 2022-04-08

Quote: “entered into two bridge promissory notes, one in an aggregate principal amount of $60 million with B. Riley Commercial Capital, LLC and one in an aggregate principal amount of $15 million with an affiliate of B. Riley Commercial Capital, LLC (the "Notes"). The Notes mature on December 7, 2022, bear interest at a rate of 7% per annum and amortize in equal monthly installments starting on August 1, 2022.”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.