Washington, GA expansion capacity completion

Company: CleanSpark - Project: Washington

This claim was marked delayed on September 15, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2022-08-09
Promised by
2023-06-30
Promised amount
50.0 MW
Current status
delayed

The claim, verbatim

Additional 50 megawatts of capacity expected to be available at Washington, GA facility by mid-2023

Source (primary)

CleanSpark 10-Q filed 2022-08-10 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “with an additional 50 megawatts of capacity expected to be available in mid-2023”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms CleanSpark 10-Q filed 2022-08-10

Quote: “with an additional 50 megawatts of capacity expected to be available in mid-2023”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.