Marathon Digital Holdings hosting contract
Company: Applied Digital - Project: Ellendale
The claim, verbatim
Five-year hosting contract with Marathon for 200 MW capacity: 90 MW at Texas facility and at least 110 MW at North Dakota facility, with option for additional 70 MW
Source (primary)
Applied Digital 10-K filed 2022-08-29 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “Additionally, on July 12, 2022, the Company entered into a five-year hosting contract with Marathon Digital Holdings, Inc. ("Marathon") for 200 MW of mining capacity. As a result of this arrangement, the Company will supply Marathon with 90 MW of hosting capacity at its facility in Texas and at least 110 MW of hosting capacity at its second facility in North Dakota. As part of this agreement, the Company has also provided Marathon with the option to increase hosting capacity utilizing up to an additional 70 MW in North Dakota, which would increase the total amount of hosting across all of the Company's facilities to 270 megawatts if the option is exercised.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Applied Digital 10-K filed 2022-08-29
Quote: “Additionally, on July 12, 2022, the Company entered into a five-year hosting contract with Marathon Digital Holdings, Inc. ("Marathon") for 200 MW of mining capacity. As a result of this arrangement, the Company will supply Marathon with 90 MW of hosting capacity at its facility in Texas and at least 110 MW of hosting capacity at its second facility in North Dakota. As part of this agreement, the Company has also provided Marathon with the option to increase hosting capacity utilizing up to an additional 70 MW in North Dakota, which would increase the total amount of hosting across all of the Company's facilities to 270 megawatts if the option is exercised.”