1.21 Gigawatts capacity up to 1.5 GW
Company: Applied Digital
The claim, verbatim
1.21 Gigawatts will develop, acquire, and construct Next-Gen datacenters with up to 1.5 GW capacity
Source (primary)
Applied Digital 10-K filed 2022-08-29 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “1.21 Gigawatts will develop, acquire, construct, finance, operate, maintain and own one or more Next-Gen datacenters with up to 1.5 gigawatts ("GW") of capacity”
How we checked this
Checked on September 22, 2026. The cited source supports every part of this claim.
The document states 1.21 Gigawatts will develop datacenters with up to 1.5 gigawatts of capacity.
Confirmed in the source:
- 1.21 Gigawatts will develop, acquire and construct Next-Gen datacenters with up to 1.5 GW of capacity
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000162828022023816/apld-20220531.htm) in full (312,378 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 10-K filed 2022-08-29
Quote: “1.21 Gigawatts will develop, acquire, construct, finance, operate, maintain and own one or more Next-Gen datacenters with up to 1.5 gigawatts ("GW") of capacity”