Promised amount
500.0 MW
Current status
stated

The claim, verbatim

Applied Digital expects to begin construction on a third co-hosting facility in North Dakota, resulting in total combined capacity of approximately 500 MW.

Source (primary)

Applied Digital 424B3 filed 2022-09-27 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “We also expect to begin construction in North Dakota on our third facility, resulting in a total combined capacity of roughly 500 MW.”

How we checked this

Checked on September 22, 2026. The cited source supports every part of this claim.

The document states the third North Dakota facility is expected and the roughly 500 MW combined capacity.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487922000044/a9262022424b3finalprospect.htm) in full (350,225 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 424B3 filed 2022-09-27

Quote: “We also expect to begin construction in North Dakota on our third facility, resulting in a total combined capacity of roughly 500 MW.”

View cached copy (2026-09-13)Live source ↗