Co-location data center availability schedule
Company: CleanSpark - Project: Sandersville
What the later record shows
Outcome not yet confirmed
No passage says when the co-location modular data centers were emptied.
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Co-location modular data centers must be emptied on or before day 195 after closing (April 21, 2023) for full earn-out; later deliveries result in pro-rata reduction
Source (primary)
CleanSpark 8-K filed 2022-10-11 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “with 100% of the Earn-Out Shares being available with respect to Co-location MDCs that are emptied on or before the 195 th day after the Closing Date, and 84% of the Earn-out Shares being available with respect to Co-location MDCs that are emptied on the 196 th day after the Closing Date”
How we checked this
Checked on October 11, 2026. The cited source supports part of this claim, but not all of it.
The day-195 deadline is accurate, but the filing describes a stepped schedule that ends at a cutoff, not a pro rata reduction, and it does not say emptying is mandatory.
Confirmed in the source:
- The full earn-out requires co-location modular data centers to be emptied on or before day 195 after closing, which is April 21, 2023
- The earn-out percentage falls for data centers emptied later
We could not confirm this from the cited source:
- That the reduction for later emptying is pro rata; the filing describes a drop to 84% on day 196, then a further 1 percentage point per day, with no shares earnable after a cutoff
- That the data centers must be emptied; the filing presents emptying them only as a condition for the earn-out
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000095017022019412/clsk-20221008.htm) in full (12,436 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms CleanSpark 8-K filed 2022-10-11
Quote: “with 100% of the Earn-Out Shares being available with respect to Co-location MDCs that are emptied on or before the 195 th day after the Closing Date, and 84% of the Earn-out Shares being available with respect to Co-location MDCs that are emptied on the 196 th day after the Closing Date”