jain.com

Joint venture with Antpool for blockchain datacenter development

Company: Applied Digital

Subject kind
partnership
Statement date
2023-05-15
Promised amount
1.5 GW
Current status
stated

The claim, verbatim

Applied Digital and Antpool formed 1.21 Gigawatts LLC with 80/20 ownership to develop, construct, and operate Next-Gen datacenters with up to 1.5 gigawatts of capacity for blockchain infrastructure

Source (primary)

Applied Digital 424B3 filed 2023-05-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “On January 6, 2022, we and Antpool, an affiliate of Bitmain Technologies Holding Company, entered into a Limited Liability Company Agreement of 1.21 Gigawatts, LLC ('1.21 Gigawatts'), pursuant to which we and Antpool contributed $8,000 and $2,000, respectively, and will initially own 80% and 20%, respectively, of 1.21 Gigawatts. 1.21 Gigawatts will develop, acquire, construct, finance, operate, maintain and own one or more Next-Gen datacenters with up to 1.5 gigawatts ('GW') of capacity for hosting blockchain infrastructure.”

How we checked this

Checked on September 21, 2026. The cited source supports every part of this claim.

The document states all of these facts about the Antpool joint venture.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487923000134/apld-424b3finalprospectus0.htm) in full (53,370 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 424B3 filed 2023-05-16

Quote: “On January 6, 2022, we and Antpool, an affiliate of Bitmain Technologies Holding Company, entered into a Limited Liability Company Agreement of 1.21 Gigawatts, LLC ('1.21 Gigawatts'), pursuant to which we and Antpool contributed $8,000 and $2,000, respectively, and will initially own 80% and 20%, respectively, of 1.21 Gigawatts. 1.21 Gigawatts will develop, acquire, construct, finance, operate, maintain and own one or more Next-Gen datacenters with up to 1.5 gigawatts ('GW') of capacity for hosting blockchain infrastructure.”

View cached copy (2026-09-13)Live source ↗