jain.com

Initial purchase order of 33,280 Bitcoin mining servers

Company: Riot

Subject kind
product
Statement date
2023-06-29
Promised by
2024-04-15
Promised amount
33280.0 units
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed

The 2023 10-K says MicroBT miner deliveries under the broader Master Agreement began in Q4 2023, with all miners expected by mid-2025. Its M56S++ count (22,684) differs from the initial order's 24,960, and no passage confirms the 33,280-miner initial order was fully delivered by April 15, 2024.

“Delivery of the miners began in the fourth quarter of 2023, with all miners expected to be received and deployed by mid-2025.”
2024-02-22 · Riot 10-K filed 2024-02-23 View cached copy (2026-09-13)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Riot and MicroBT executed initial purchase order for 33,280 Miners (8,320 M56S+ and 24,960 M56S++ models) with delivery in monthly installments from November 15, 2023 to April 15, 2024.

Source (primary)

Riot 8-K filed 2023-06-30 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “Riot and MicroBT executed an initial purchase order of 33,280 Miners (including 8,320 model M56S+ Miners and 24,960 model M56S++ Miners) to be delivered in monthly installments of approximately 5,400 Miners, between November 15, 2023, and April 15, 2024”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The filing states the initial order's size, model breakdown and monthly delivery window exactly as claimed.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1167419/000155837023011660/riot-20230626x8k.htm) in full (26,985 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot 8-K filed 2023-06-30

Quote: “Riot and MicroBT executed an initial purchase order of 33,280 Miners (including 8,320 model M56S+ Miners and 24,960 model M56S++ Miners) to be delivered in monthly installments of approximately 5,400 Miners, between November 15, 2023, and April 15, 2024”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 14, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.