jain.com

Combined installed self-mining capacity across six operating sites

Company: Hut 8 - Project: Granbury

Subject kind
facility capacity
Statement date
2023-08-23
Promised amount
7.5 EH/s
Current status
stated

The claim, verbatim

New Hut will have combined installed self-mining capacity of 7.5 EH/s and 253 MW of energy across six sites: Medicine Hat and Drumheller in Alberta; Niagara Falls in New York; Kearney in Nebraska; and Granbury and King Mountain in Texas

Source (primary)

Hut 8 S-4/A filed 2023-08-24 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “New Hut is expected to benefit from a combined installed self-mining capacity of 7.5 exahashes per second ("EH/s") and 253 megawatts ("MW") of total energy currently available from six sites with current self-mining operations: Medicine Hat, Alberta; Drumheller, Alberta; Niagara Falls, New York; Kearney, Nebraska; Granbury, Texas; and King Mountain, Texas.”

How we checked this

Checked on September 21, 2026. The cited source supports every part of this claim.

The document states verbatim the combined 7.5 EH/s, 253 MW, and the six named self-mining sites.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1964789/000110465923094950/tm235928-21_s4a.htm) in full (1,238,196 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Hut 8 S-4/A filed 2023-08-24

Quote: “New Hut is expected to benefit from a combined installed self-mining capacity of 7.5 exahashes per second ("EH/s") and 253 megawatts ("MW") of total energy currently available from six sites with current self-mining operations: Medicine Hat, Alberta; Drumheller, Alberta; Niagara Falls, New York; Kearney, Nebraska; Granbury, Texas; and King Mountain, Texas.”

View cached copy (2026-09-13)Live source ↗