Corsicana Facility initial phase: 400 MW immersion-cooled infrastructure
Company: Riot - Project: Corsicana
The claim, verbatim
Initial phase of Corsicana Facility development involves construction of 400 megawatts of immersion-cooled Bitcoin Mining and Data Center Hosting infrastructure, including high-voltage power substation and transmission facilities
Source (primary)
Riot 10-K filed 2024-02-23 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “The initial phase of the development of the Corsicana Facility involves the construction of 400 megawatts ("MW") of immersion-cooled Bitcoin Mining and Data Center Hosting infrastructure, as well as a high-voltage power substation and transmission facilities”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Riot 10-K filed 2024-02-23
Quote: “The initial phase of the development of the Corsicana Facility involves the construction of 400 megawatts ("MW") of immersion-cooled Bitcoin Mining and Data Center Hosting infrastructure, as well as a high-voltage power substation and transmission facilities”