Fluidstack Abernathy lease
Company: TeraWulf - Project: Abernathy HPC Campus
The claim, verbatim
TeraWulf signed 168 MW Fluidstack lease at Abernathy JV.
Source (primary)
terawulf 8-K exhibit (terawulfq42025investorpr.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-13)Live source ↗
Quote: “Signed 168 MW Fluidstack lease at Abernathy JV”
How we checked this
Checked on September 21, 2026. The cited source supports every part of this claim.
Slide 3 lists 'Signed 168 MW Fluidstack lease at Abernathy JV'.
Confirmed in the source:
- TeraWulf signed a 168 MW Fluidstack lease at Abernathy JV
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330126000026/terawulfq42025investorpr.htm) in full (29,065 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (terawulfq42025investorpr.htm)
Quote: “Signed 168 MW Fluidstack lease at Abernathy JV”