jain.com

ERCOT interconnection approval for Hunt County

Company: Core Scientific

Subject kind
regulatory
Statement date
2026-03-01
Current status
stated

The claim, verbatim

Power and ramp schedule for Hunt County approved through ERCOT interconnection process in October 2024

Source (primary)

core-scientific 8-K exhibit (q4fy25earningsdeckvfinal.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-13)Live source ↗

Quote: “Power and ramp schedule approved through ERCOT interconnection process in October 2024”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms core-scientific 8-K exhibit (q4fy25earningsdeckvfinal.htm)

Quote: “Power and ramp schedule approved through ERCOT interconnection process in October 2024”

View cached copy (2026-09-13)Live source ↗