Price adjustment in Phase II GPU lease agreement

Company: Applied Digital

This claim was marked delayed on September 11, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
customer
Statement date
2026-07-23
Promised by
2025-08-01
Promised amount
26910720.0 USD
Current status
delayed

The claim, verbatim

On April 29, 2024, Applied Digital and Character Tech. entered into Second Addendum updating Phase II pricing to $2.25 per GPU per hour for 1,024 GPUs over 16 months, with total Phase II contract value of $26,910,720.00, and lease term extended from March 2024 to August 2025.

Source (primary)

Docket 279 entry #32 - 1 (RECAP, court_filing)
View cached copy (2026-09-10)Live source ↗

Quote: “Applied Digital alleges that the Second Addendum provided a price of $2.25 per GPU, per hour, assessed on a 24-hour per-day, 7-day per-week basis for the 1,024 GPUs over the remaining 16 months of the Agreement, with a total Phase II Tranche value of $26,910,720.00. Applied Digital asserts that pursuant to the Second Addendum, Character Tech. would continue to lease both the Phase I Tranche and the Phase II Tranche GPUs from March 2024 to August 2025.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Docket 279 entry #32 - 1

Quote: “Applied Digital alleges that the Second Addendum provided a price of $2.25 per GPU, per hour, assessed on a 24-hour per-day, 7-day per-week basis for the 1,024 GPUs over the remaining 16 months of the Agreement, with a total Phase II Tranche value of $26,910,720.00. Applied Digital asserts that pursuant to the Second Addendum, Character Tech. would continue to lease both the Phase I Tranche and the Phase II Tranche GPUs from March 2024 to August 2025.”

View cached copy (2026-09-10)Live source ↗

Record of changes

September 10, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 11, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.