Kearney
Project of Marathon Digital
Where it stands
Marathon acquired the operating Kearney, NE bitcoin mining site on January 12, 2024, together with Granbury, TX. The 390 MW acquisition figure covers both sites combined. Marathon's FY2024 10-K lists Kearney at 92 MW operational, with 8 MW of growth capacity toward 100 MW nameplate, subject to approvals. The 2026 10-K still lists the GC Data Center Kearney, LLC subsidiary, but none of the passages give updated Kearney capacity after March 2025.
92 MW in service · 8 MW planned
| Phase | MW | Status | Date | Source |
|---|---|---|---|---|
| Kearney site (existing operational capacity) | 92 | operational | 2025-03-02 | Kearney, Nebraska Grid connection 92 8 100 5.8 2025-03-02 View cached copy (2026-08-31)Live source ↗ |
| Kearney growth capacity | 8 | planned | Kearney, Nebraska Grid connection 92 8 100 5.8 2025-03-02 View cached copy (2026-08-31)Live source ↗ |
Assessed November 1, 2026 from the newest filings, releases and reporting that name this project (newest relied on: March 2, 2026).
Claims about this project
Site intelligence
How we located this site
- Starting point (the project's stated locality) 2026-11-01
Kearney, NE → 40.69933, -99.08168 (locality) - No site-level evidence yet 2026-11-01
no address, road, landmark or coordinates tie this project to a specific parcel yet -- the town is shown, NOT the site - OpenStreetMap features nearby 2026-11-01
0 named match(es)
Satellite imagery on this page is drawn from the Google Earth satellite basemap. Each image is dated, labelled by source and pixel resolution, and downloadable at its native size; cloudy dates are kept and marked rather than hidden. New scenes are pulled daily as each provider publishes them.