jain.com

Ulysses site energization target

Company: Cipher Mining - Project: Ulysses Site

Subject kind
facility timeline
Statement date
2026-02-23
Promised by
2027-12-31
Current status
stated

The claim, verbatim

Ulysses Site expected to energize in fourth quarter 2027.

Source (primary)

Cipher Mining 10-K filed 2026-02-24 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “The Ulysses Site is expected to energize in the fourth quarter of 2027”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Cipher Mining 10-K filed 2026-02-24

Quote: “The Ulysses Site is expected to energize in the fourth quarter of 2027”

View cached copy (2026-08-31)Live source ↗