Mikeska gross capacity

Company: Cipher Mining - Project: Mikeska Site

Subject kind
facility capacity
Statement date
2026-05-04
Promised by
2028-01-01
Promised amount
500.0 MW
Current status
stated

The claim, verbatim

Mikeska will have 500 MW of gross capacity.

Source (primary)

cipher-mining 8-K exhibit (exh992cipherdigital_busi.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-08)Live source ↗

Quote: “500 MW Gross Capacity”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document states Mikeska has 500 MW gross capacity.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000181998926000025/exh992cipherdigital_busi.htm) in full (22,565 characters, retrieved September 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cipher-mining 8-K exhibit (exh992cipherdigital_busi.htm)

Quote: “500 MW Gross Capacity”