Current operating and contracted capacity
Company: Cipher Mining
The claim, verbatim
Cipher currently operates and has contracted 907 MW of gross capacity.
Source (primary)
cipher-mining 8-K exhibit (exh992cipherdigital_busi.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-08)Live source ↗
Quote: “907 MW (1) of operating and contracted capacity today, including three data center campus leases with world's leading hyperscalers”
How we checked this
Checked on September 19, 2026. The cited source supports every part of this claim.
The document states 907 MW of operating and contracted capacity today, with a note indicating figures are based on gross MWs.
Confirmed in the source:
- Cipher has 907 MW of operating and contracted capacity today
- The 907 MW figure is on a gross basis
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000181998926000025/exh992cipherdigital_busi.htm) in full (22,565 characters, retrieved September 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms cipher-mining 8-K exhibit (exh992cipherdigital_busi.htm)
Quote: “907 MW (1) of operating and contracted capacity today, including three data center campus leases with world's leading hyperscalers”