jain.com

Chesapeake Data acquisition pending regulatory approval

Company: TeraWulf

Subject kind
acquisition
Statement date
2026-05-07
Promised amount
210.0 MW
Current status
stated

The claim, verbatim

Chesapeake Data acquisition (approximately 210 MW grid-connected generation capacity, expandable to 1 GW) remains subject to customary regulatory approvals including FERC

Source (primary)

terawulf 8-K exhibit (a_wulfearningsreleaseq1202.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-08)Live source ↗

Quote: “Acquisition remains subject to customary regulatory approvals, including FERC”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document confirms the 210 MW capacity, the 1 GW expansion ability, and the pending FERC/regulatory approvals.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330126000083/a_wulfearningsreleaseq1202.htm) in full (21,699 characters, retrieved September 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (a_wulfearningsreleaseq1202.htm)

Quote: “Acquisition remains subject to customary regulatory approvals, including FERC”

View cached copy (2026-09-08)Live source ↗