jain.com

Connected power guidance 2026

Company: Nebius

Subject kind
facility capacity
Statement date
2026-05-12
Promised by
2026-12-31
Promised amount
900.0 MW
Current status
stated

The claim, verbatim

Expect 800 MW to 1 GW of connected power by year-end 2026

Source (primary)

nebius 8-K exhibit (tm2614392d1_ex99-2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-07)Live source ↗

Quote: “We continue to expect 800MW to 1GW of connected power by year-end.”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document states this connected power expectation for year-end.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1513845/000110465926059872/tm2614392d1_ex99-2.htm) in full (43,236 characters, retrieved September 7, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms nebius 8-K exhibit (tm2614392d1_ex99-2.htm)

Quote: “We continue to expect 800MW to 1GW of connected power by year-end.”

View cached copy (2026-09-07)Live source ↗