jain.com

Total AI Portfolio Contracted IT Capacity

Company: Hut 8

Subject kind
facility capacity
Statement date
2026-07-19
Promised amount
949.0 MW
Current status
stated

The claim, verbatim

Total contracted IT capacity across Hut 8's AI data center portfolio is 949 MW

Source (primary)

hut-8 8-K exhibit (tm2620835d1_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-03)Live source ↗

Quote: “Total contracted IT capacity across Hut 8's AI data center portfolio rises to 949 MW”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document states the portfolio's total contracted IT capacity rises to 949 MW.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1964789/000110465926084862/tm2620835d1_ex99-1.htm) in full (13,326 characters, retrieved September 3, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms hut-8 8-K exhibit (tm2620835d1_ex99-1.htm)

Quote: “Total contracted IT capacity across Hut 8's AI data center portfolio rises to 949 MW”

View cached copy (2026-09-03)Live source ↗