Beacon Point Utility Capacity

Company: Hut 8 - Project: Beacon Point

Subject kind
facility capacity
Statement date
2026-07-19
Promised amount
1000.0 MW
Current status
stated

The claim, verbatim

Beacon Point has 1,000 MW of utility capacity secured under interconnection agreement with AEP Texas

Source (primary)

hut-8 8-K exhibit (tm2620835d1_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-03)Live source ↗

Quote: “its 1,000 MW of utility capacity, secured under an interconnection agreement with AEP Texas”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document states the 1,000 MW of utility capacity is secured under an interconnection agreement with AEP Texas.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1964789/000110465926084862/tm2620835d1_ex99-1.htm) in full (13,326 characters, retrieved September 3, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms hut-8 8-K exhibit (tm2620835d1_ex99-1.htm)

Quote: “its 1,000 MW of utility capacity, secured under an interconnection agreement with AEP Texas”

View cached copy (2026-09-03)Live source ↗