Reveille 70 MW ERCOT interconnection approved
Company: Cipher Mining
The claim, verbatim
Reveille interconnection approved for 70 gross MW by ERCOT with substation development initiated
Source (primary)
cipher-mining 8-K exhibit (cipherdigital_businessup.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-02)Live source ↗
Quote: “ERCOT interconnection approved for 70 gross MW and substation development initiated”
How we checked this
Checked on September 19, 2026. The cited source supports every part of this claim.
Stated verbatim in the Reveille section.
Confirmed in the source:
- Reveille interconnection approved for 70 gross MW by ERCOT
- Substation development initiated
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm) in full (22,200 characters, retrieved September 2, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms cipher-mining 8-K exhibit (cipherdigital_businessup.htm)
Quote: “ERCOT interconnection approved for 70 gross MW and substation development initiated”