jain.com

Total contracted AI data center capacity and expected contract value

Company: Hut 8

Subject kind
facility capacity
Statement date
2026-08-14
Promised amount
949.0 MW
Current status
stated

The claim, verbatim

Total contracted AI data center capacity is 949 megawatts representing approximately $26.6 billion of expected aggregate base-term contract value

Source (primary)

Hut 8 (HUT) Q2 2026 Earnings Call Transcript - AOL.com (-, news_article)
View cached copy (2026-08-31)Live source ↗

Quote: “total contracted AI data center capacity is about 949 megawatts, representing roughly $26.6 billion of expected aggregate base-term contract value”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document states total contracted AI data center capacity is about 949 megawatts representing roughly $26.6 billion of expected aggregate base-term contract value.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.aol.com/articles/hut-8-hut-q2-2026-171448000.html) in full (83,559 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Hut 8 (HUT) Q2 2026 Earnings Call Transcript - AOL.com

Quote: “total contracted AI data center capacity is about 949 megawatts, representing roughly $26.6 billion of expected aggregate base-term contract value”

View cached copy (2026-08-31)Live source ↗