Company: CleanSpark

Subject kind
facility timeline
Statement date
2026-08-14
Current status
stated

The claim, verbatim

CleanSpark will build its own substation and pay the utility for necessary upgrades to serve the project

Source (primary)

Austin County residents protest CleanSpark data center in Sealy - Click2Houston (-, news_article)
View cached copy (2026-08-31)Live source ↗

Quote: “CleanSpark Chief Business Officer Harry Sudocks said the company would build its own substation and pay the utility for necessary upgrades to serve the project.”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document attributes both assertions to CleanSpark's Chief Business Officer Harry Sudocks.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.click2houston.com/news/local/2026/08/15/austin-county-residents-protest-cleanspark-data-center-in-sealy/) in full (7,830 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Austin County residents protest CleanSpark data center in Sealy - Click2Houston

Quote: “CleanSpark Chief Business Officer Harry Sudocks said the company would build its own substation and pay the utility for necessary upgrades to serve the project.”

View cached copy (2026-08-31)Live source ↗