Chief Facility expansion potential
Company: Cipher Mining - Project: Chief Facility
The claim, verbatim
Chief Facility has capacity to expand up to 115 MW subject to applicable regulatory approvals
Source (primary)
Cipher Mining 10-K filed 2025-02-25 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “The Chief Facility has the capacity to expand up to 115 MW, subject to applicable regulatory approvals”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Cipher Mining 10-K filed 2025-02-25
Quote: “The Chief Facility has the capacity to expand up to 115 MW, subject to applicable regulatory approvals”