Core42 72.5 MW in 2025
Company: TeraWulf
What the later record shows
The date slipped · new target March 31, 2026
Only 18 critical IT MW of HPC capacity was energized at Lake Mariner at the end of 2025, and later materials show the 60 MW Core42 contract delivering from July 2025 to March 2026. No passage ties the 72.5 MW figure to the 60 MW critical IT figure, so this rests on the shortfall at year-end 2025.
“As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
“60 MW Jul ’25 – Mar ’26 378 MW Jun ‘26 – Mar ’27”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked November 5, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf's leased capacity schedule shows 72.5 MW for Core42 in 2025.
Source (primary)
WULF Expands Fluidstack Deal (IR page (investors.terawulf.com), ir_release)
View cached copy (2026-11-05)Live source ↗Archive.org ↗
Quote: “Core42: 72.5 MW in 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms WULF Expands Fluidstack Deal
Quote: “Core42: 72.5 MW in 2025”
delays Q2 2026 Earnings Update Presentation
Quote: “60 MW Jul ’25 – Mar ’26 378 MW Jun ‘26 – Mar ’27”
delays View 10-K PDF
Quote: “As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity”