Core42 72.5 MW in 2025

Company: TeraWulf

This claim was marked delayed on November 5, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2025-09-04
Promised by
2025-12-31
Promised amount
72.5 MW
Current status
delayed

What the later record shows

The date slipped · new target March 31, 2026

Only 18 critical IT MW of HPC capacity was energized at Lake Mariner at the end of 2025, and later materials show the 60 MW Core42 contract delivering from July 2025 to March 2026. No passage ties the 72.5 MW figure to the 60 MW critical IT figure, so this rests on the shortfall at year-end 2025.

“As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
“60 MW Jul ’25 – Mar ’26 378 MW Jun ‘26 – Mar ’27”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked November 5, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf's leased capacity schedule shows 72.5 MW for Core42 in 2025.

Source (primary)

WULF Expands Fluidstack Deal (IR page (investors.terawulf.com), ir_release)
View cached copy (2026-11-05)Live source ↗Archive.org ↗

Quote: “Core42: 72.5 MW in 2025”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms WULF Expands Fluidstack Deal

Quote: “Core42: 72.5 MW in 2025”

View cached copy (2026-11-05)Live source ↗Archive.org ↗

delays Q2 2026 Earnings Update Presentation

Quote: “60 MW Jul ’25 – Mar ’26 378 MW Jun ‘26 – Mar ’27”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

delays View 10-K PDF

Quote: “As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

November 5, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 5, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.