The claim, verbatim

Eligible energy-efficiency projects are existing, retrofitted or upgraded data center infrastructure with a PUE of 1.45 or below, and new-build data center assets with a PUE of 1.4 or below.

Source (primary)

TeraWulf Green Finance Framework 2025 (IR page (investors.terawulf.com), ir_release)
View cached copy (2026-11-05)Live source ↗

Quote: “Existing, retrofitted, or upgraded data center infrastructure with a PUE = 1.45 or below • New-build data center assets with a PUE = 1.4 or below”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms TeraWulf Green Finance Framework 2025

Quote: “Existing, retrofitted, or upgraded data center infrastructure with a PUE = 1.45 or below • New-build data center assets with a PUE = 1.4 or below”