10 EH/s operating capacity reached

Company: IREN

Subject kind
facility capacity
Statement date
2024-05-14
Promised amount
10.0
Current status
stated

The claim, verbatim

IREN's operating capacity reached 10 EH/s in May 2024, up from 5.6 EH/s in December 2023, which the company says was ahead of schedule.

Source (primary)

iren 8-K exhibit (ef20027345_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-05)Live source ↗

Quote: “Operating capacity currently 10 EH/s (May 2024) vs. 5.6 EH/s (December 2023)”