jain.com

510MW planned data center capacity by end of 2024

Company: IREN

Subject kind
facility capacity
Statement date
2024-05-14
Promised by
2024-12-31
Promised amount
510.0 MW
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed · happened December 31, 2024

IREN's December 2024 monthly update reports 510MW operating at month-end, which meets the end-2024 target.

Checked November 5, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

IREN plans 510MW of data center capacity by the end of 2024, up from a previous plan of 460MW, enabled partly by a new substation design and construction and procurement improvements.

Source (primary)

iren 8-K exhibit (ef20027345_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-05)Live source ↗

Quote: “510MW of planned data center capacity by the end of 2024”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (ef20027345_ex99-1.htm)

Quote: “510MW of planned data center capacity by the end of 2024”

View cached copy (2026-11-05)Live source ↗

Record of changes

November 5, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 5, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.