15,380 T21 miners shipped before June 2024
Company: IREN
What the later record shows
Delivered; the record does not say when
The 20-F filed in August 2024 says all T21 miners under the November 2023 contract were delivered in full. It gives no shipment or delivery date, so whether this met the before-June 2024 target cannot be determined.
“All Bitmain T21 miners under this purchase contract have been delivered in full.”
2024-08-27 · IREN 20-F filed 2024-08-28 View cached copy (2026-08-31)Live source ↗
Checked November 5, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN's November 2023 Bitmain agreement, with its option exercised in December 2023, covers 15,380 T21 miners expected to be shipped in full before June 2024.
Source (primary)
iren 8-K exhibit (ef20027345_ex99-4.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-05)Live source ↗
Quote: “an option to increase to 15,380 new-generation Bitmain T21 miners with an additional hashrate of 1.6 EH/s (for an additional $22.3 million) that was exercised in December 2023 which are expected to be shipped in full before June 2024”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (ef20027345_ex99-4.htm)
Quote: “an option to increase to 15,380 new-generation Bitmain T21 miners with an additional hashrate of 1.6 EH/s (for an additional $22.3 million) that was exercised in December 2023 which are expected to be shipped in full before June 2024”
confirms IREN 20-F filed 2024-08-28
Quote: “All Bitmain T21 miners under this purchase contract have been delivered in full.”