Childress and miner option decisions during 2024

Company: IREN

This claim was marked delayed on November 5, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
guidance
Statement date
2024-05-14
Promised by
2024-12-31
Current status
delayed

What the later record shows

The date slipped · new target December 31, 2025

The August 2024 20-F widened the decision window from 2024 to 2024 and 2025. Some miner options were exercised in June 2024, but the remaining S21 Pro options were not exercised until January 2, 2025, after the original deadline.

“Decisions with respect to the Childress expansion and exercising all, some or none of the miner purchase options will be made during 2024 and 2025”
2024-08-27 · IREN 20-F filed 2024-08-28 View cached copy (2026-08-31)Live source ↗
“On June 13, 2024, we exercised options for 17,950 S21 Pro miners with a total hashrate of 4.2 EH/s”
2025-03-19 · iren 8-K exhibit (irenlimited-exx992sep2024x.htm) View cached copy (2026-10-18)Live source ↗
“On January 2, 2025, we exercised options for the remaining 30,050 S21 Pro miners, with a total hashrate of 7.0 EH/s”
2025-03-19 · iren 8-K exhibit (irenlimited-exx992dec2024x.htm) View cached copy (2026-10-18)Live source ↗

Checked November 5, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

IREN says decisions on the Childress expansion and on exercising all, some or none of its miner purchase options will be made during 2024, depending on market conditions, shareholder value and funding availability.

Source (primary)

iren 8-K exhibit (ef20027345_ex99-4.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-05)Live source ↗

Quote: “Decisions with respect to the Childress expansion and exercising all, some or none of the miner purchase options will be made during 2024”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (ef20027345_ex99-4.htm)

Quote: “Decisions with respect to the Childress expansion and exercising all, some or none of the miner purchase options will be made during 2024”

View cached copy (2026-11-05)Live source ↗

delays IREN 20-F filed 2024-08-28

Quote: “Decisions with respect to the Childress expansion and exercising all, some or none of the miner purchase options will be made during 2024 and 2025”

View cached copy (2026-08-31)Live source ↗

delays iren 8-K exhibit (irenlimited-exx992sep2024x.htm)

Quote: “On June 13, 2024, we exercised options for 17,950 S21 Pro miners with a total hashrate of 4.2 EH/s”

View cached copy (2026-10-18)Live source ↗

delays iren 8-K exhibit (irenlimited-exx992dec2024x.htm)

Quote: “On January 2, 2025, we exercised options for the remaining 30,050 S21 Pro miners, with a total hashrate of 7.0 EH/s”

View cached copy (2026-10-18)Live source ↗

Record of changes

November 5, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 5, 2026 — delayed