Total platform capacity

Company: TeraWulf

Subject kind
facility capacity
Statement date
2026-05-14
Current status
stated

The claim, verbatim

The total platform is 2,870 MW gross and 2,272 MW critical IT, with 522 MW contracted and 1,750 MW open.

Source (primary)

Q1 2026 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-05)Live source ↗Archive.org ↗

Quote: “Total Platform (Gross) Total Platform (Critical IT) 2,870 MW 2,272 MW”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Q1 2026 Earnings Update Presentation

Quote: “Total Platform (Gross) Total Platform (Critical IT) 2,870 MW 2,272 MW”

View cached copy (2026-11-05)Live source ↗Archive.org ↗