Miners secured for 40 EH/s in 1H 2025
Company: IREN
What the later record shows
Delivered on time · happened June 30, 2025
The June 2025 update (published 2025-07-06) shows Childress at 40.1 EH/s plus 9.9 EH/s at the BC sites, about 50 EH/s installed. That exceeds the 40 EH/s 1H 2025 capacity the secured miners were meant to support.
“Childress, TX 750MW Operating (650MW) | 40.1 EH/s Under Construction H2 2025 (50MW IT Load)”
2025-07-06 · iren 8-K exhibit (ef20051646_ex99-1.htm) View cached copy (2026-10-11)Live source ↗
“Mackenzie, BC 80MW Operating | 5.2 EH/s Prince George, BC 50MW Operating | 3.1 EH/s Canal Flats, BC 30MW Operating | 1.6 EH/s”
2025-07-06 · iren 8-K exhibit (ef20051646_ex99-1.htm) View cached copy (2026-10-11)Live source ↗
Checked November 4, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN says it has secured enough miners to support 40 EH/s in the first half of 2025.
Source (primary)
iren 8-K exhibit (ef20030723_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-04)Live source ↗
Quote: “Miners secured to support 40 EH/s in 1H 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (ef20030723_ex99-1.htm)
Quote: “Miners secured to support 40 EH/s in 1H 2025”
confirms iren 8-K exhibit (ef20051646_ex99-1.htm)
Quote: “Childress, TX 750MW Operating (650MW) | 40.1 EH/s Under Construction H2 2025 (50MW IT Load)”