ERCOT Batch Zero final classifications
Company: Cipher Mining
The claim, verbatim
Cipher received ERCOT Batch Zero classifications including a conditional base-load classification for 1 GW at Mikeska, and expects final classifications in December after a data-center audit.
Source (primary)
What Cipher Mining (CIFR) Said on Its Q3 Earnings Call - TradingView (-, news_article)
View cached copy (2026-11-03)Live source ↗Archive.org ↗
Quote: “The company expects final classifications in December following completion of a data-center audit.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms What Cipher Mining (CIFR) Said on Its Q3 Earnings Call - TradingView
Quote: “The company expects final classifications in December following completion of a data-center audit.”