Contracted HPC campuses revenue backlog

Company: Cipher Mining

Subject kind
customer
Statement date
2026-11-02
Promised amount
16600000000.0 USD
Current status
stated

The claim, verbatim

Cipher's three contracted HPC campuses total 700 gross MW and about $16.6 billion of contracted revenue over the next two decades, with a 17.3-year weighted average term and up to about $28.4 billion if all extensions are exercised.

Source (primary)

What Cipher Mining (CIFR) Said on Its Q3 Earnings Call - TradingView (-, news_article)
View cached copy (2026-11-03)Live source ↗Archive.org ↗

Quote: “its three contracted HPC campuses total 700 gross megawatts and represent approximately $16.6 billion of contracted revenue over the next two decades”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms What Cipher Mining (CIFR) Said on Its Q3 Earnings Call - TradingView

Quote: “its three contracted HPC campuses total 700 gross megawatts and represent approximately $16.6 billion of contracted revenue over the next two decades”