jain.com

Barber Lake cost per IT MW

Company: Cipher Mining

Subject kind
guidance
Statement date
2026-11-02
Promised amount
13000000.0 USD/MW
Current status
stated

The claim, verbatim

Cipher expects Barber Lake's cost to rise to about $13 million per IT megawatt, up from the prior financed $10.4 million per IT megawatt.

Source (primary)

What Cipher Mining (CIFR) Said on Its Q3 Earnings Call - TradingView (-, news_article)
View cached copy (2026-11-03)Live source ↗Archive.org ↗

Quote: “Cipher expects Barber Lake's cost to rise to about $13 million per IT megawatt, compared with the prior financed cost of $10.4 million per IT megawatt”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms What Cipher Mining (CIFR) Said on Its Q3 Earnings Call - TradingView

Quote: “Cipher expects Barber Lake's cost to rise to about $13 million per IT megawatt, compared with the prior financed cost of $10.4 million per IT megawatt”

View cached copy (2026-11-03)Live source ↗Archive.org ↗