Hashrate target 3Q 2024
Company: IREN
What the later record shows
Delivered on time · happened September 30, 2024
The September 2024 update shows 21 EH/s operating, and the November update confirms installed capacity had been 21 EH/s before rising to 28 EH/s. Both exceed the 20 EH/s 3Q 2024 target.
“Childress (Texas, USA) 200 11.1 Complete Operating Total Operating 360 21”
2024-10-03 · iren 8-K exhibit (irensepmonthlyupdate4oct.htm) View cached copy (2026-10-26)Live source ↗
“28 EH/s (15 J/TH) installed capacity at month-end, up by 33% from 21 EH/s (16 J/TH)”
2024-12-05 · iren 8-K exhibit (nov2024monthlyupdatevdc.htm) View cached copy (2026-10-24)Live source ↗
Checked November 1, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN is on track to reach 20 EH/s of installed hashrate in 3Q 2024.
Source (primary)
iren 8-K exhibit (junemonthlyinvestorupdat.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-01)Live source ↗
Quote: “On track for 20 EH/s in 3Q 2024”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (junemonthlyinvestorupdat.htm)
Quote: “On track for 20 EH/s in 3Q 2024”
confirms iren 8-K exhibit (nov2024monthlyupdatevdc.htm)
Quote: “28 EH/s (15 J/TH) installed capacity at month-end, up by 33% from 21 EH/s (16 J/TH)”
confirms iren 8-K exhibit (irensepmonthlyupdate4oct.htm)
Quote: “Childress (Texas, USA) 200 11.1 Complete Operating Total Operating 360 21”