Finland data center expansion completion
Company: Nebius
What the later record shows
The date slipped · new target December 31, 2025
In October 2024 Nebius said the Finnish expansion would triple capacity to 75MW by the end of 2025 or early 2026, later than the 12-month target of July 2025. No passage confirms completion. It is unclear whether the original claim referred only to Phase I.
“Finnish data center expansion : expected to triple power capacity to 75MW by the end of 2025 or early 2026”
2024-10-17 · nebius 8-K exhibit (tm2426436d1_ex99-1.htm) View cached copy (2026-10-25)Live source ↗
Checked November 1, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Nebius has started expanding its Finnish data center and plans to complete the expansion within the next 12 months.
Source (primary)
nebius 8-K exhibit (tmb-20240716xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-01)Live source ↗
Quote: “We also have started to expand our data center in Finland, and we plan to complete it over the next 12 months.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms nebius 8-K exhibit (tmb-20240716xex99d2.htm)
Quote: “We also have started to expand our data center in Finland, and we plan to complete it over the next 12 months.”
delays nebius 8-K exhibit (tm2426436d1_ex99-1.htm)
Quote: “Finnish data center expansion : expected to triple power capacity to 75MW by the end of 2025 or early 2026”