Cheyenne site 30 MW power capacity

Company: CleanSpark

Subject kind
facility capacity
Statement date
2024-07-31
Promised amount
30.0 MW
Current status
stated

The claim, verbatim

The first Wyoming site in Cheyenne has a power capacity of 30 MW and is planned to run as a fully immersion-cooled facility.

Source (primary)

cleanspark 8-K exhibit (clsk-ex99_1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-31)Live source ↗

Quote: “The first site, with a power capacity of 30 MW”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms cleanspark 8-K exhibit (clsk-ex99_1.htm)

Quote: “The first site, with a power capacity of 30 MW”

View cached copy (2026-10-31)Live source ↗