Paris colocation data center on stream
Company: Nebius
What the later record shows
Delivered; the record does not say when
In October 2024 the Paris site was still described as 'to be put into operation by the end of November 2024'. The 2025 20-F lists Paris among Nebius's data centers alongside reported connected capacity, but no passage says when it went live.
“(3) To be put into operation by the end of November 2024”
2024-10-17 · nebius 8-K exhibit (tm2426436d1_ex99-1.htm) View cached copy (2026-10-25)Live source ↗
“As of March 31, 2025, we had approximately 45MW of connected capacity across both geographies, and are rapidly expanding it further.”
2025-04-29 · Nebius 20-F filed 2025-04-30 View cached copy (2026-08-31)Live source ↗
“Paris, France – in July 2024 we signed an agreement for our Paris data center, our first co-location facility.”
2025-04-29 · Nebius 20-F filed 2025-04-30 View cached copy (2026-08-31)Live source ↗
Checked October 31, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Nebius AI signed an agreement in early July 2024 to rent a colocation data center in Paris and plans to bring it on stream by November 2024.
Source (primary)
nebius 8-K exhibit (tmb-20240630xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-31)Live source ↗
Quote: “We plan to bring this new data center on stream by November 2024.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms nebius 8-K exhibit (tmb-20240630xex99d1.htm)
Quote: “We plan to bring this new data center on stream by November 2024.”
confirms Nebius 20-F filed 2025-04-30
Quote: “As of March 31, 2025, we had approximately 45MW of connected capacity across both geographies, and are rapidly expanding it further.”
confirms nebius 8-K exhibit (tm2426436d1_ex99-1.htm)
Quote: “(3) To be put into operation by the end of November 2024”